Q1 Several BoMs per product? Confirmed
Answer Yes
-
Q2 A + B = C + D Confirmed
Answer Enable By-Products setting; add by-products on the BoM
-
Q3 Component forecast updated Confirmed
Answer At MO confirmation
-
Q4 OEE "fully productive" time Confirmed
Answer Recorded time not exceeding the expected time
-
Q5 OEE measures Confirmed
Answer Efficiency of a work center
-
Q6 Subcontracting setup Confirmed
Answer BoM Type = Subcontracting + subcontractor
-
Q7 2-step MO, extra component consumed in WO Likely
Answer No new picking; qty at pre-production location decreases
-
Q8 Work-order dependencies Confirmed
Answer Enable in Manufacturing settings AND on the BoM Miscellaneous tab
-
Q9 Shop Floor "Register Production" Confirmed
Answer Register units produced
-
Q10 Shop Floor "Mark as Done" on a WO card Confirmed
Answer Card fades; next WO appears
-
Q11 Work-center "Allowed Employees" empty Confirmed
Answer Any employee can work there
-
Q12 "Fully productive" work center Confirmed
Answer Processing a WO within expected duration
-
Q13 "Reduced speed" Confirmed
Answer Processing a WO that exceeded expected duration
-
Q14 "Comparison" on MRP reports Confirmed
Answer Compare two time periods
-
Q15 Measures drop-down Confirmed
Answer Select the dataset (measure) shown
-
Q16 Kit as a BoM component? Confirmed
Answer Yes
-
Q17 Quality control points on receipts? Confirmed
Answer Yes
-
Q18 Invoice a repair via SO Confirmed
Answer Both parts and operations can go on the SO
-
Q19 MPS orange cell Likely
Answer Replenishment already ordered but not enough to reach safety stock (green = OK, red = too much)
-
Q20 Work-center capacity Confirmed
Answer Units it can produce in parallel
-
Q21 Product-specific capacity on a work center Confirmed
Answer Yes
-
Q22 Capacity 3, BoM makes 4, 10 min/cycle Confirmed
Answer 20 min
-
Q23 Overview of component lead times & availability Verify in Odoo
Answer BoM Overview
-
Q24 Start a WO timer in Shop Floor Confirmed
Answer Click the header of the WO card
-
Q25 Split/merge MOs Verify in Odoo
Answer Merge only MOs of the same product and same BoM (draft/confirmed)
-
Q26 NOT on a Shop Floor MO card Likely
Answer Estimated time to complete the MO
-
Q27 Cost of a specific work order Confirmed
Answer MO > Overview > Operations section
-
Q28 Analytic account on an MO Verify in Odoo
Answer Consumed components and WO costs are posted (negative)
-
Q29 Different lots tested separately Likely
Answer QCP Control per = Quantity
-
Q30 MPS "Actual Demand Y-1 / Y-2" Confirmed
Answer Quantity sold at this time last year / two years ago
-
Q31 Click "Check Availability" on an MO (Shop Floor) Likely
Answer After replenishing a scrapped component
-
Q32 Production analysis for one product Confirmed
Answer Type the product in the search bar
-
Q33 Repair stock moves Likely
Answer Parts reserved on confirm, consumed when the repair ends